Task Properties |
The Task type exposes the following members.
| Name | Description | |
|---|---|---|
| ActualEndDate |
The actual end date of the task.
| |
| ActualStartDate |
The actual start date of the task.
| |
| ActualWorkAmount |
The amount of work already used for the task.
| |
| Completeness |
The percentage of the completeness of the task on the scale from 0 to 100.
| |
| Critical |
The criticality of the task.
| |
| Description |
A short textual description of the task.
| |
| Identifier |
The identifier of the object.
(Inherited from Object.) | |
| IsUpToDate | Gets if the object does not have a modification which is not shared. (Inherited from ModelObject.) | |
| Local |
The locality indicates if the task was created in Tekla Structures and Task Manager or imported.
| |
| ModificationTime | Gets latest time of the object was modified or created. (Inherited from ModelObject.) | |
| Name |
The name of the task.
| |
| PlannedEndDate |
The planned end date of the task.
| |
| PlannedStartDate |
The planned start date of the task.
| |
| PlannedWorkAmount |
The amount of work planned to be used for the task.
| |
| Scenario |
The scenario which the task belongs to.
| |
| Url |
A link to material or data related to the task. The link can be a hyperlink or a file system link.
|